Project # Monopole Tower #234
Client XYZ Construction
Status In Progress
Date Created 08-04-2025
Start-Date 08-04-2025
Deadline 31-07-2025
Project Progress
60%
Description
  • Work of construction of 132kV SC line form 132kV Shendra-Chikalthana using monopole structure with ACCC high ampacity conductor-12 kM under Aurangabad zone on turnkey basis against tender no. T-2117 (RFx: 6000000991)

Administrative Work

Sr.No Date Work Status Remark File Action
1 16-09-2025 LOA Received View File
2 29-09-2022 LOA Acceptance Submitted
3 16-09-2025 Security Deposite Submitted View File
4 29-09-2022 Contract Agreement Submitted View File
5 16-09-2025 Purchase Order Pending View File
6 29-09-2022 Insurance Submitted View File
7 16-09-2025 BOQ Submitted View File
8 29-09-2022 TBC Submitted View File
Sr.No Date Approvals Status Remark File Action
1 16-09-2025 Foundation Approval Approved View File
2 29-09-2022 Monopole Approval Approved View File
3 16-09-2025 Conductor Approval Approved View File
4 29-09-2022 Hardware Approval Approved
5 16-09-2025 Insulator Approval Pending View File
6 16-09-2025 Miscellaneous Items Pending View File
Sr.No Date Procurement Status Remark Action
1 16-09-2025 Monopoles Supplied 53 poles Delivered
2 29-09-2022 Conductor Pending
3 16-09-2025 Hardware Supplied
4 29-09-2022 Insulator Pending
5 29-09-2022 Miscellaneous Items Pending
Sr.No Date Inspection Status Remark File Action
1 16-09-2025 Monopoles Done View File
2 29-09-2022 Conductor Pending
3 16-09-2025 Hardware Done
4 29-09-2022 Insulator Pending
5 29-09-2022 Miscellaneous Items Pending
6 29-09-2022 Miscellaneous Work/Activities Pending
Sr.No Date Dispatch Status Remark File Action
1 16-09-2025 Monopoles Done View File
2 29-09-2022 Conductor Pending
3 16-09-2025 Hardware Done
4 29-09-2022 Insulator Pending
5 29-09-2022 Miscellaneous Items Pending
6 29-09-2022 Miscellaneous Work/Activities Pending
Sr.No Date JMC Status Remark Action
1 16-09-2025 Foundation of Monopoles Done 20 Poles
2 16-09-2025 Erection of Monopoles Done 11 Poles
3 16-09-2025 Stringing of Conductor Pending
Sr.No Date MRC Status Remark Action
1 16-09-2025 Monopoles Done
2 16-09-2025 Conductor Done
3 16-09-2025 Hardware Pending
4 16-09-2025 Insulator Pending

Line Work Tasks

Sr.No Task Date Status Remark Action
1 Site Visit 09-04-2025 Completed
2 Site Handover 11-04-2025 In Progress
3 Survey 09-04-2025 Completed
4 Profile 11-04-2025 Submitted
5 Miscellaneous Works 11-04-2025 In Progress

Civil Work Tasks

Sr.No Task Date Status Remark Action
1 ROW 09-04-2025 Completed
2 Soil Testing 11-04-2025 In Progress
3 Foundation of Monopoles 09-04-2025 Completed
4 Erection of Monopoles 11-04-2025 Submitted
5 Miscellaneous Works 11-04-2025 In Progress

Electrical Work Tasks

Sr.No Task Date Status Remark Action
1 Stringing of Conductor 09-04-2025 Completed
2 Testing 11-04-2025 In Progress
3 Commissioning 09-04-2025 Completed
4 Miscellaneous Works 11-04-2025 In Progress

Substation Work Tasks

Sr.No Task Date Status Remark Action
1 SLD 09-04-2025 Completed
2 Check Survey 11-04-2025 In Progress
3 Civil Work - Formation of Gantry Structure 09-04-2025 Completed
4 Civil Work - Erection of Gantry Structure 11-04-2025 Submitted
5 Civil Work - Formation of Equipment Structure 11-04-2025 In Progress
6 Civil Work - Erection of Equipment Structure 09-04-2025 Completed
7 Civil Work - Miscellaneous Works 11-04-2025 In Progress
8 Electrical Work - Testing of Equipment's 09-04-2025 Completed
9 Electrical Work - Commissioning of Substation 11-04-2025 Submitted
10 Electrical Work - Miscellaneous Works 11-04-2025 In Progress
11 Substation JMC - Foundations of Equipment's 11-04-2025 Submitted
12 Substation MRC - Substation Equipment's 11-04-2025 In Progress

Members List

  • Mahesh B - Engineer
  • Mayur C - Helper
  • Anil V - Civil Engineer
  • Sagar G - Electrician