Project Details - Monopole Tower #234
- Home
- Project Details
| Project # | Monopole Tower #234 |
| Client | XYZ Construction |
| Status | In Progress |
| Date Created | 08-04-2025 |
| Start-Date | 08-04-2025 |
| Deadline | 31-07-2025 |
| Project Progress |
60%
|
Description
- Work of construction of 132kV SC line form 132kV Shendra-Chikalthana using monopole structure with ACCC high ampacity conductor-12 kM under Aurangabad zone on turnkey basis against tender no. T-2117 (RFx: 6000000991)
Administrative Work
| Sr.No | Date | Work | Status | Remark | File | Action |
|---|---|---|---|---|---|---|
| 1 | 16-09-2025 | LOA | Received | View File | ||
| 2 | 29-09-2022 | LOA Acceptance | Submitted | |||
| 3 | 16-09-2025 | Security Deposite | Submitted | View File | ||
| 4 | 29-09-2022 | Contract Agreement | Submitted | View File | ||
| 5 | 16-09-2025 | Purchase Order | Pending | View File | ||
| 6 | 29-09-2022 | Insurance | Submitted | View File | ||
| 7 | 16-09-2025 | BOQ | Submitted | View File | ||
| 8 | 29-09-2022 | TBC | Submitted | View File |
Approvals
| Sr.No | Date | Approvals | Status | Remark | File | Action |
|---|---|---|---|---|---|---|
| 1 | 16-09-2025 | Foundation Approval | Approved | View File | ||
| 2 | 29-09-2022 | Monopole Approval | Approved | View File | ||
| 3 | 16-09-2025 | Conductor Approval | Approved | View File | ||
| 4 | 29-09-2022 | Hardware Approval | Approved | |||
| 5 | 16-09-2025 | Insulator Approval | Pending | View File | ||
| 6 | 16-09-2025 | Miscellaneous Items | Pending | View File |
Procurement
Inspection
| Sr.No | Date | Inspection | Status | Remark | File | Action |
|---|---|---|---|---|---|---|
| 1 | 16-09-2025 | Monopoles | Done | View File | ||
| 2 | 29-09-2022 | Conductor | Pending | |||
| 3 | 16-09-2025 | Hardware | Done | |||
| 4 | 29-09-2022 | Insulator | Pending | |||
| 5 | 29-09-2022 | Miscellaneous Items | Pending | |||
| 6 | 29-09-2022 | Miscellaneous Work/Activities | Pending |
Dispatch
| Sr.No | Date | Dispatch | Status | Remark | File | Action |
|---|---|---|---|---|---|---|
| 1 | 16-09-2025 | Monopoles | Done | View File | ||
| 2 | 29-09-2022 | Conductor | Pending | |||
| 3 | 16-09-2025 | Hardware | Done | |||
| 4 | 29-09-2022 | Insulator | Pending | |||
| 5 | 29-09-2022 | Miscellaneous Items | Pending | |||
| 6 | 29-09-2022 | Miscellaneous Work/Activities | Pending |
JMC
MRC
Line Work Tasks
Civil Work Tasks
Electrical Work Tasks
Substation Work Tasks
| Sr.No | Task | Date | Status | Remark | Action |
|---|---|---|---|---|---|
| 1 | SLD | 09-04-2025 | Completed | ||
| 2 | Check Survey | 11-04-2025 | In Progress | ||
| 3 | Civil Work - Formation of Gantry Structure | 09-04-2025 | Completed | ||
| 4 | Civil Work - Erection of Gantry Structure | 11-04-2025 | Submitted | ||
| 5 | Civil Work - Formation of Equipment Structure | 11-04-2025 | In Progress | ||
| 6 | Civil Work - Erection of Equipment Structure | 09-04-2025 | Completed | ||
| 7 | Civil Work - Miscellaneous Works | 11-04-2025 | In Progress | ||
| 8 | Electrical Work - Testing of Equipment's | 09-04-2025 | Completed | ||
| 9 | Electrical Work - Commissioning of Substation | 11-04-2025 | Submitted | ||
| 10 | Electrical Work - Miscellaneous Works | 11-04-2025 | In Progress | ||
| 11 | Substation JMC - Foundations of Equipment's | 11-04-2025 | Submitted | ||
| 12 | Substation MRC - Substation Equipment's | 11-04-2025 | In Progress |
Members List
- Mahesh B - Engineer
- Mayur C - Helper
- Anil V - Civil Engineer
- Sagar G - Electrician